Reading passage
The Lartigue Monorail Experiment
Skip to the questions ↓During the rapid industrial expansion of the late nineteenth century, conventional twin-rail networks transformed inland commerce across the globe. However, establishing standard railways in remote or topographically challenging environments presented formidable obstacles. Laying twin parallel tracks required substantial capital, extensive earthmoving, and continuous ballast maintenance, which often rendered projects financially unviable in sparsely populated rural regions. In response, several engineers sought alternative designs that could reduce construction expenditure while coping with difficult terrain. Among the most distinctive of these innovations was the elevated single-rail system conceived by a French civil engineer named Charles Lartigue. His concept drew direct inspiration from transport methods he had observed in North Africa, where loaded panniers were slung across the backs of camels to maintain equilibrium across shifting sands.
The core principle of the Lartigue design was deceptively simple: instead of resting on two parallel ground rails, vehicles straddled a single elevated central rail. This steel running rail was mounted on a series of triangular, A-shaped steel trestles anchored into simple sleepers or foundation blocks. To prevent the rolling stock from tilting excessively as it travelled, two auxiliary guide rails were affixed to the outer lower legs of each trestle, roughly half a metre above ground level. Guide wheels extending from the lower flanks of the carriages pressed against these stabilising tracks. By elevating the main weight-bearing rail approximately one metre into the air, the system largely eliminated the need to level the ground beneath it, allowing lines to follow the natural contours of hilly or undulating landscapes with minimal excavation.
Early trials in the late 1870s and early 1880s demonstrated the potential of the concept for lightweight haulage. In North Africa, portable manual and animal-drawn versions were deployed to transport esparto grass across desert terrain, proving remarkably resilient in conditions where shifting sand routinely buried conventional railway beds. Subsequent public demonstrations in European capitals generated considerable interest, prompting railway promoters to consider steam-powered versions for public transport. Because the elevated track structure could be prefabricated and rapidly assembled by relatively small work crews, advocates argued that the Lartigue system represented the ideal solution for opening up underdeveloped rural districts that lacked the traffic density to justify traditional railway lines.
The most famous practical test of the technology occurred in southwest Ireland, where a passenger and freight line connecting the coastal towns of Listowel and Ballybunion commenced operation in 1888. Spanning roughly fifteen kilometres, this railway relied on purpose-built steam locomotives featuring twin boilers positioned on either side of the central rail to ensure symmetry. The operational reality of the line, however, demanded meticulous weight management. Carriages were divided into two parallel longitudinal halves, and station masters had to carefully distribute passengers to prevent severe imbalances. When agricultural goods or livestock were carried, handlers were frequently obliged to split loads or even pair heavy animals, such as calves, with equally heavy sacks of sand on the opposing side to maintain stability.
Despite its successful daily operation over several decades, the Lartigue system suffered from profound mechanical and infrastructural limitations. Foremost among these was the extreme difficulty of designing junctions and switches. On a traditional railway, switches consist of movable rail sections that divert wheel flanges seamlessly from one track to another. On an elevated monorail, such an arrangement was impossible because the entire supporting trestle structure blocked lateral movement. Consequently, changing tracks required massive, pivoting turntable segments that had to be physically rotated to connect different lines. Similarly, road crossings posed an enormous nuisance; because vehicles could not simply drive over an elevated beam, the railway line had to be constructed with drawbridge-style lifting sections that had to be operated by hand whenever a road carriage wished to cross.
Maintenance also proved more complex than initial estimates had suggested. Although the trestles did not require heavy ballast, the lateral forces exerted on the lower guide rails caused substantial friction and uneven wheel wear. The locomotives, with their dual-boiler layouts and mirrored mechanical linkages, were labour-intensive to service, requiring engineers to duplicate maintenance tasks across both sides of the machinery. While the capital investment needed to construct the permanent way had indeed been lower than that of a standard line, these ongoing operating and maintenance expenses gradually eroded the system's economic advantage.
The line in southwest Ireland survived until the early 1920s, outlasting other experimental installations before succumbing to financial losses exacerbated by civil conflict and road competition. Although the Lartigue monorail did not achieve widespread global adoption, modern transport historians view it as a pivotal evolutionary step in transport engineering. It demonstrated that single-rail vehicles could reliably provide scheduled public services over complex terrain, laying foundational concepts regarding centre-of-gravity management and modular track construction that would later re-emerge in modern elevated urban monorails.
Questions 1–8
Choose the correct letter, A, B, C or D.
1What prompted the development of the Lartigue elevated single-rail system?
- AA desire to replace pack animals with faster mechanical alternatives.
- BThe inability of standard trains to travel safely on sandy soil.
- CPublic opposition to large-scale infrastructure projects in rural areas.
- DThe high financial and logistical demands of traditional railway construction.
2How did the Lartigue system maintain the stability of moving trains?
- ABy anchoring deep foundation blocks directly beneath the central rail.
- BBy utilising side guide wheels running against lower stabilising rails.
- CBy restricting the maximum height of passenger carriages.
- DBy keeping the main running rail as close to the ground as possible.
3What advantage did early trials in North Africa reveal about the system?
- AIt remained functional in conditions that disrupted conventional tracks.
- BIt could be operated without any human supervision.
- CIt could carry heavier freight than standard steam engines.
- DIt eliminated the need for routine maintenance in desert areas.
4According to the passage, running the railway line in southwest Ireland required operators to
- Arestrict travel to certain times of day to ensure safety.
- Bavoid carrying heavy farm animals on passenger services.
- Crebuild carriages to accommodate different types of freight.
- Densure cargo and passengers were evenly balanced on both sides.
5Why were track junctions particularly difficult to create on the Lartigue monorail?
- AThe elevated structure obstructed standard sideways track movements.
- BThe train drivers could not see the switches from their cabins.
- CThe metal rails expanded unpredictably in changing temperatures.
- DThe weight of the locomotives damaged traditional switch points.
6What is mentioned about road crossings along the monorail route?
- AThey caused frequent collisions with horse-drawn carriages.
- BThey had to be built above the level of the monorail tracks.
- CThey required manual adjustment to allow road vehicles to cross.
- DThey were only permitted in areas with minimal vehicular traffic.
7What was the primary reason the system's initial financial advantages diminished over time?
- AThe rapid increase in the cost of raw steel for replacement trestles.
- BUnexpectedly high expenditure on ongoing servicing and operational upkeep.
- CThe requirement to pay compensation to traditional railway companies.
- DThe expense of replacing tracks damaged by severe weather.
8In the final paragraph, the writer suggests that the Lartigue monorail
- Afailed primarily due to flaws in its foundational engineering theories.
- Bwould have survived if it had been introduced in more urbanised locations.
- Cmade valuable contributions to the later development of single-rail transport.
- Dwas quickly forgotten after the closure of the line in southwest Ireland.
Ready to answer these 8 questions?
Log in to attempt this drill in the BandLadder test player, with instant scoring when you finish.
Ready for a full Reading test?
Three passages, 40 questions of every type and 60 minutes on the clock, with your band score the moment you finish. Your free account also gets AI-scored Writing and Speaking.
Take a full timed test free →Keep practising
More Multiple Choice drills
Get your band, not just a score
- ✓Full timed Reading and Listening tests
- ✓AI-scored Writing with band feedback
- ✓AI-scored Speaking with an AI examiner
Free account · no card
© 2026 BandLadder. Written and checked by the BandLadder team. You may quote or cite this page with credit to BandLadder and a link to it; republishing it in full needs our written permission. Content use policy