IELTS Reading · Table Completion

Techniques in Urban Tunnelling

Read the passage and the 8 Table Completion questions below. To attempt the drill, log in free: it opens in the BandLadder test player with instant scoring.
  • 8 questions
  • 855 words
  • About 10 minutes
  • Free account

Reading passage

Techniques in Urban Tunnelling

Skip to the questions ↓

Constructing subterranean transport corridors beneath modern cities is among the most demanding branches of civil engineering. Unlike rural excavation through solid bedrock, urban tunnelling must navigate unconsolidated soils, fluctuating water tables, and a dense tangle of pre-existing foundations, sewers, and utility conduits. Furthermore, engineers must strictly limit surface settlement—the downward movement of the ground above the excavation—because even minor subsidence can crack building facades, deform historic architecture, and rupture critical water pipes. Over the past two centuries, subterranean engineering has evolved from rudimentary manual digging into an exact and sophisticated science. Engineers have developed several distinct tunnelling techniques, each designed to address specific geological conditions, depth requirements, and urban constraints, balancing economic expenditure against the absolute necessity of maintaining public safety and structural preservation throughout the project lifecycle.

The earliest systematic urban technique was the cut-and-cover method, widely adopted during the initial expansion of metropolitan underground railways in the nineteenth century. In its conventional form, known as bottom-up construction, workers excavated a wide, deep trench along existing street corridors, constructed side walls and a sturdy roof slab, and then backfilled the cavity before reinstating the roadway above. A later refinement, known as the top-down approach, involved sinking retaining walls first and casting the permanent concrete slab at ground level, allowing vehicular traffic and surface activities to resume while excavation proceeded underneath the protective cover. While cut-and-cover remains highly cost-effective for shallow transit stations and straightforward alignment profiles, its open-trench nature inevitably causes immense disruption to surface traffic and requires the complex, costly relocation of buried pipes and cables.

To avoid disturbing street life altogether, engineers turned to shield tunnelling, a concept originally pioneered for excavating soft ground beneath navigable rivers and subsequently adapted for subterranean railways deep beneath congested urban centres. The fundamental innovation of this method was a rigid circular cylinder, known as a shield, which supported the unstable perimeter of the bore while labourers excavated material at the front face. As the excavation advanced, powerful hydraulic rams pushed the shield forward, and workers assembled precast segmental rings behind it to establish a permanent, load-bearing lining. Early shields substantially reduced the incidence of catastrophic collapses in waterlogged soils, though the reliance on manual excavation within an open chamber exposed miners to considerable physical hazard, poor air quality, and severely restricted the pace of daily advance.

The hazards and limitations of open shields eventually spurred the development of mechanised, closed-face Tunnel Boring Machines (TBMs), which currently dominate large-scale transit construction across the globe. In these massive apparatuses, a rotating cutter head replaces manual digging, while a pressurised chamber directly behind the cutting wheel balances hydrostatic and earth pressures in real time. In Earth Pressure Balance (EPB) machines, the excavated soil itself is pressurised and regulated through a screw conveyor to balance ground forces. In slurry shields, a bentonite fluid is pumped into the cutterhead to support the face, after which the liquefied spoil is extracted through pipelines to a surface separation plant. These sealed systems maintain ground stability with extraordinary precision, preventing settlement even beneath fragile historic structures, although the machines require substantial financial investment and long manufacturing lead times.

In contrast to the rigid geometry of circular TBMs, the Sequential Excavation Method—often referred to as the New Austrian Tunnelling Method (NATM)—offers superior flexibility for constructing complex underground caverns, crossover junctions, and non-circular stations. Rather than resisting ground pressure with thick, inflexible precast segments, this technique treats the surrounding geological formation as an active structural component. Workers excavate the ground in carefully controlled stages and immediately apply shotcrete—a fast-setting sprayed concrete—reinforced with steel arches and rock bolts to stabilise the newly exposed perimeter. Crucially, the method permits controlled, minor ground deformation, which mobilises the rock mass's innate load-bearing capacity before final secondary linings are installed. Sophisticated digital instruments monitor real-time convergence, though the approach requires exceptional geological expertise and remains vulnerable in loose, water-bearing strata where unconfined ground cannot self-support.

Modern urban excavation projects rarely rely on a single tunnelling method in isolation; rather, engineers frequently integrate supplementary ground-engineering techniques to manage unforeseen hazards and stabilise precarious strata. In water-saturated silt or gravel, artificial ground freezing is sometimes employed, circulating chilled brine through drilled pipes to convert unstable soil into a temporary barrier of frozen earth. Similarly, compensation grouting involves injecting cementitious mixtures under pressure beneath sensitive foundations to counteract settlement as a tunnel passes below. By pairing advanced excavation machinery with predictive numerical modelling, geotechnical drilling, and real-time monitoring sensors, contemporary civil engineers can construct intricate underground networks while keeping surface city life almost entirely undisturbed.

Ultimately, the choice of tunnelling methodology depends on a complex calculation involving local geology, tunnel depth, surface constraints, and project budgets. While mechanical tunnel boring machines remain the undisputed standard for lengthy transit tunnels driven through consistent ground conditions, sequential excavation continues to be indispensable for bespoke underground geometry and station caverns. Meanwhile, cut-and-cover retains its utility for shallow infrastructure where surface space permits. As urban densities increase worldwide, the refinement of these complementary excavation methods ensures that modern cities can expand their subterranean transit capacity while preserving the historic fabric and everyday functionality of the world above.

Questions 1–8

Complete the table below. Choose NO MORE THAN TWO WORDS from the passage for each answer.

Word limit: NO MORE THAN TWO WORDS

Comparison of Urban Tunnelling Techniques

MethodCore Mechanism and SupportKey AdvantagesMain Drawbacks
Cut-and-coverDigging a trench; installing side walls and a durable 1Economical for shallow station constructionSignificant interference with 2; requirement to move underground pipes and cables
Classical shieldA hollow metal cylinder propelled by 3; lining made of segmented ringsLower risk of serious collapses in wet soilsHigh danger for workers; slow construction speed due to manual digging
Closed-face TBMsA mechanical cutter wheel; a pressurised area; transport of excavated soil or 4 via augers or pipelinesExtremely accurate; avoids 5 near delicate architectureHigh machinery costs; extensive production lead times
Sequential Excavation (NATM)Phased digging followed by immediate coverage with 6; structural monitoringHighly flexible for non-standard stations and large 7Needs high geotechnical skill; ineffective in loose, 8

Ready to answer these 8 questions?

Log in to attempt this drill in the BandLadder test player, with instant scoring when you finish.

Ready for a full Reading test?

Three passages, 40 questions of every type and 60 minutes on the clock, with your band score the moment you finish. Your free account also gets AI-scored Writing and Speaking.

Take a full timed test free →

Keep practising

More Table Completion drills

Get your band, not just a score

  • ✓Full timed Reading and Listening tests
  • ✓AI-scored Writing with band feedback
  • ✓AI-scored Speaking with an AI examiner
Take a full timed test free

Free account · no card

© 2026 BandLadder. Written and checked by the BandLadder team. You may quote or cite this page with credit to BandLadder and a link to it; republishing it in full needs our written permission. Content use policy

Log in to attempt — free